In early 2017, Trans Mountain Pipeline filed seven applications under section 21 of the National Energy Board Act (NEB Act) to change or vary the Certificate. Under section 21 of the NEB Act, a company may request a change to a decision that has already been made. In this case, Trans Mountain has applied to the NEB to change the general corridor approved for the Project.

The seven route realignments that Trans Mountain has applied for below are listed in the table below. They are listed in the order the applications were received.

Oral Hearings for Segment 7
Variance Location Length of Reroute Status
Edmonton ATCO Right of Way Route Realignment
[Folder 3311861]
Edmonton, AB 252 m Approved

NEB Decision: [Filing A88794]
Edmonton LRT Route Realignment
[Folder 3311427]
Edmonton, AB 1.66 km Approved

NEB Decision: [Filing A88795]
Kawkawa Lake Indian Reserve Route Realignment
[Folder 3310984]
Hope, BC 21 m Approved

NEB Decision: [Filing A88791]
Westsyde Road Route Realignment
[Folder 3311532]
Black Pines, BC 89 m Approved

NEB Decision: [Filing A88793]
Sumas Tank Farm Route Realignment
[Folder 3311096]
Abbotsford, BC 800 m Approved

NEB Decision: [Filing A88792]
ICBC Parking Lot Route Realignment
[Folder 3311646]
Coquitlam, BC 403 m Approved

NEB Decision: [Filing A88790]
Chilliwack BC Hydro Route Realignment
Project webpage
Chilliwack, BC 1.8 km Approved

NEB Decision: [Filing A91053]

Contacts Us

Telephone (toll free): 1-800-899-1265
E-mail: TMX.ProcessHelp@cer-rec.gc.ca
Fax: 403-292-5503
Toll free fax: 1-877-288-8803

Media Inquiries

Media Relations Team
Canada Energy Regulator
Email: media@cer-rec.gc.ca
Telephone (toll free): 1-800-899-1265

Date modified: