NOVA Gas Transmission Ltd. – Northwest Mainline Loop (Boundary Lake North Section)

What’s New

  • 31 July 2018: NEB Decision for NGTL’s Northwest Mainline Loop
  • 4 May 2018: Northwest Mainline Loop (Boundary Lake North Section) Hearing Order Issued [Filing A91767]
  • 15 December 2017: NOVA Gas Transmission Ltd. submits project application [Filing A88650]

Project Information

NOVA Gas Transmission Ltd (NGTL) has applied, pursuant to section 58 of the National Energy Board Act (NEB Act), to construct 23 kilometres of pipeline within Clear Hills County, Alberta. The Project is proposed to transport sweet natural gas from a tie in connection adjacent to the Owl Lake South Meter Station to the existing Hidden Lake Compressor Station (Project). The Project will parallel existing disturbance, for the majority of the route. Once constructed, all new above-ground facilities will be located within a fenced area.

The Project will be located approximately 140 km northwest of Manning, Alberta within Treaty 8 territory.

The Project will be located on Provincial Crown land, and will require approximately 62 hectares of new permanent land and approximately 24 hectares of temporary work space for construction.

Project Map

This map provides an overview of the Northwest Mainline Loop (Boundary Lake North Section).

Northwest Mainline Loop (Boundary Lake North Section) Map

View larger PDF version [PDF 3113 KB]

Key Milestones

  • 4 May 2018: Northwest Mainline Loop (Boundary Lake North Section) Hearing Order Issued [Filing A91767]
  • 15 December 2017: NOVA Gas Transmission Ltd. submits project application [Filing A88650]

Resources

If you would like to learn more about how the NEB’s hearing process and how to participate, as well as how the Board regulates pipelines, please visit the following links:

Apply to Participate

To be a participant in a NEB hearing process, you must be directly affected or have relevant information or expertise. You can apply to participate as an intervenor or by letter of comment.

Participant Funding Program

The application deadline has passed. For recipients that have signed a contribution agreement, you must submit a claim form [PDF 166 KB] to receive payment for your eligible costs incurred. For more information about the PFP, visit our Participant Funding Program page, or contact a PFP Coordinator at 1-800-899-1265.

Contacts

Company contacts

If you have questions about the Project, please contact TransCanada or contact Jason Dyble.

Mr. Jaron Dyble
NOVA Gas Transmission Ltd.
450 – 1 Street SW
Calgary, AB  T2P 5H1
Phone: 403-920-5214
Facsimile: 403-920-2347
Email: jaron_dyble@transcanada.com

NEB Contacts

E-mail: BoundaryLake@cer-rec.gc.ca
Telephone: 403-292-4800
Telephone (toll free): 1-800-899-1265
Facsimile: 403-292-5503
Facsimile (toll free): 1-877-288-8803

For assistance filing documents on the Board’s website, please contact:

Rachel Clark
Process Advisor Team

Canada Energy Regulator
Email: rachel.clark@cer-rec.gc.ca
Telephone: 403-389-4240
Telephone (toll free): 1-800-899-1265
Facsimile: 403-292-5503
Facsimile (toll free): 1-877-288-8803

For media inquiries, please contact:

Marc Drolet
Communications Officer
Canada Energy Regulator
Email: Marc.Drolet@cer-rec.gc.ca
Telephone: 514-476-9911
Telephone (toll free): 1-800-899-1265

Date modified: