2025–26 Annual Report of the Commission of the Canada Energy Regulator - Appendix D: Time Limits
2025-26 Time Limits
Under the CER Act, the Lead Commissioner must set a time limit for certain types of applications. The time limit must not exceed the maximum number of days stated in the CER Act. The Commission must complete its assessment and make its recommendation or decision within this time limit. The standard time limits set by the Lead Commissioner can be found on the CER website.
The following table shows applications which were subject to time limits for processing under the CER Act. In the 2025-26 fiscal year, 16 non-hearing applications, 2 hearing applications, and 2 export licences were issued within time limits set under the CER Act. Please note that the average completion timeline for the three section 214 categories is as follows:
- Category A – 62 days
- Category B – 108 days
- Category C – 179 days
The overall average was 98 days.
Table D.1: Large Pipeline Infrastructure Applications
| Legislation | Application Type | Time Limit | Application | Days from Completeness to Decision Issued | Decision | Time Limit Met? |
|---|---|---|---|---|---|---|
| CER Act s 183 |
Large Pipeline Infrastructure | 430 days from application complete | Pouce Coupé Pipe Line Ltd. – Application for the Taylor to Gordondale Pipeline Project | 406 | C37235 | Yes |
| CER Act s 183 |
Large Pipeline Infrastructure | 450 days from application complete | Westcoast Energy GP Inc. on behalf of Westcoast Energy Limited Partnership - Application for the Sunrise Expansion Program | 437 | C38105 | Yes |
Table D.2: Export Licence Applications
| Legislation | Application Type | Time Limit | Application | Days from Completeness to Decision Issued | Decision | Time Limit Met? |
|---|---|---|---|---|---|---|
| CER Act s 344 |
Export Licences | 6 months from application complete | AltaGas Ltd. - Application for Licences to Export Propane and Butane | 142 | C37007 | Yes |
| CER Act s 344 |
Export Licences | 6 months from application complete | Cedar 1 LNG Export Ltd. - Application for a Licence to Export Liquified Natural Gas | 167 | C37621 | Yes |
Table D.3: Small Pipeline Infrastructure Applications
| Legislation | Application Type | Time Limit | Application | Days from Completeness to Decision Issued | Decision | Time Limit Met? |
|---|---|---|---|---|---|---|
| CER Act s 214 |
Small Pipeline Infrastructure - Category A | 130 days from application complete | NGTL GP Ltd., as general partner on behalf of NGTL Limited Partnership - Saturn No. 3 Receipt Meter Station | 38 | C34299 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category A | 130 days from application complete | NGTL GP Ltd., as general partner on behalf of NGTL Limited Partnership - Whiskey Jack Lake Ethane Extraction Plant Tie-in | 36 | C35075 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category B | 210 days from application complete | NGTL GP Ltd., as general partner on behalf of NGTL Limited Partnership - Eastern Alberta System Mainline Control Valve and Crossover | 73 | C35131 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category B | 210 days from application complete | NGTL GP Ltd., as general partner on behalf of NGTL Limited Partnership - Central Alberta System Mainline Modifications | 66 | C35138 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category A | 130 days from application complete | NGTL GP Ltd., as general partner on behalf of NGTL Limited Partnership - Pipestone Creek Receipt Meter Station Expansion | 35 | C35796 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category A | 130 days from application complete | NGTL GP Ltd., as general partner on behalf of NGTL Limited Partnership - Tawadina Creek No. 2 Receipt Meter Station | 34 | C35806 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category C | 300 days from application complete | NGTL GP Ltd., as general partner, on behalf of NGTL Limited Partnership - Leming Lake Sales Lateral Loop (Sand Section) | 198 | C36019 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category B | 210 days from application complete | Minell Pipeline Ltd. - GS-100 McAuley Primary Gate Station Relocation | 90 | C36374 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category A | 130 days from application complete | NGTL GP Ltd. - Application for the Dawson Creek No. 2 Expansion Receipt Meter Station | 36 | C36872 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category A | 130 days from application complete | NGTL GP Ltd., as general partner on behalf of NGTL Limited Partnership - Dimsdale Interconnect Meter Station Application | 38 | C36903 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category C | 300 days from application complete | NGTL GP Ltd., as general partner on behalf of NGTL Limited Partnership - Grande Prairie Mainline Loop No. 3 (McLeod South Section) | 133 | C37914 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category C | 300 days from application complete | Pouce Coupé Pipe Line Ltd. as agent and general partner of the Pembina North Limited Partnership - Application for the NPS 10 Kiskatinaw River Replacement | 128 | C37983 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category A | 130 days from application complete | Enbridge Pipelines Inc. - Line 93 Optimization Project | 36 | C38532 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category A | 130 days from application complete | Enbridge Pipelines Inc. - Line 4 and 67 Optimization Project | 34 | C38568 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category B | 210 days from application complete | Enbridge Pipelines Inc. - Line 1 Optimization Project | 92 | C38607 | Yes |
| CER Act s 214 |
Small Pipeline Infrastructure - Category B | 210 days from application complete | NGTL GP Ltd., as general partner on behalf of NGTL Limited Partnership - Tremblay North Receipt Meter Station | 72 | C38605 | Yes |
- Date modified: