Notice to Resume Work or of Measures Satisfied – Westcoast Energy Inc. – Order DJM-001-2024
NOTICE TO RESUME WORK OR OF MEASURES SATISFIED
IN THE MATTER OF THE CANADIAN ENERGY REGULATOR ACT,
FOLLOWING AN ORDER UNDER SECTION 109(1)
The undersigned Canada Energy Regulator Inspection Officer hereby notifies:
Accountable Officer, Cynthia Hansen, of Westcoast Energy Inc. that the hazardous or detrimental situation described in Order No. DJM-001-2024 has been remedied to the satisfaction of the Inspection Officer.
Therefore,
- X suspended work may resume, and/or
- the measures specified in the order have been satisfied.
- X Specified Measures 1, 2, 3, and 5 are satisfied, while Specified Measure #4 remains in progress.
Inspection Officer | August 14 2024 | |
Date | ||
IO Designation Number | Signature | |
210-517 10 Ave SW, Calgary AB T2R 0A8 |
CVA number: CV2425-197