ARCHIVED - Westcoast Energy Inc. carrying on business as Spectra Energy Transmission (Westcoast) - Nig Creek Pipeline Rupture - Return to Service Plan

This page has been archived on the Web

Information identified as archived is provided for reference, research or recordkeeping purposes. It is not subject to the Government of Canada Web Standards and has not been altered or updated since it was archived. Please contact us to request a format other than those available.

Westcoast Energy Inc. carrying on business as Spectra Energy Transmission (Westcoast) Nig Creek Pipeline Rupture - Return to Service Plan [PDF 68 KB]

File OF-Surv-Inc-2012 81
14 August 2012

Mr. Monty Peterson
Director
Field Services Gathering
Spectra Energy Transmission
Bag Service 6180
Mile 53 Alaska Hwy.
Fort St. John, BC  V1J 4H7
Facsimile 250-262-3467

Dear Mr. Peterson:

Westcoast Energy Inc. carrying on business as Spectra Energy Transmission (Westcoast) - Nig Creek Pipeline Rupture - Return to Service Plan dated 7 August 2012

The National Energy Board (Board) is in receipt of Westcoast’s Return to Service Plan for the Nig Creek Pipeline which ruptured on 28 June 2012. The Board approves the Return to Service Plan, subject to the following modification. The Board directs that the hydrostatic pressure test (spike test) described in Point 4 of the proposed Return to Service Plan be carried out such that the test pressure (125% MOP) in the pipeline is held for five minutes following pressure stabilization in the pipeline.

The Board further directs that Westcoast apply for leave to return the pipeline to service by submitting the results of the pressure tests, for approval.

Yours Truly,

for Sheri Young
Secretary of the Board

Attachment

cc: Mr. Larry Hunt, Westcoast, Facsimile 604-691-5001
Mr. Paul Hartzheim, Westcoast, Facsimile 403-699-1585
Mr. Manuel Katchounian, TSB, Facsimile 819-953-7876