Pouce Coupé Pipe Line Ltd. – Taylor to Gordondale Pipeline Project
Project Background
Pouce Coupé Pipe Line Ltd. (Pouce Coupé), a wholly-owned subsidiary of Pembina Pipeline Corporation, is proposing to build and operate the Taylor to Gordondale Pipeline project.
The proposed project includes:
- about 89 kilometres (km) of 16-inch diameter pipeline from the existing Taylor Tank Farm Facility east of Taylor, British Columbia to the Pouce Coupé Block Valve near Gordondale, Alberta
- upgrades to the Taylor Tank Farm Facility including installation of two new electric booster pumps and two new electric mainline pumps.
The proposed pipeline will carry natural gas liquids and crude oil products. The proposed project will cross about 13 km of Crown land, about 75 km of freehold land and will parallel existing or approved linear disturbances for about 96 per cent of the route.
Pouce Coupé engaged with 63 landowners, 10 occupants, and 35 Indigenous communities potentially affected by or interested in the proposed project.
Where are we in the process?
The Commission of the CER has determined completeness, list of participants and issued a comment process for the Taylor to Gordondale pipeline application. A hearing will be scheduled so the Commission and participants can gain further insight into the application. More details will be posted once the hearing dates are confirmed.
Timeline
Engagement
The Canada Energy Regulator (CER) requires companies to conduct engagement activities with Indigenous Peoples, landowners, and other potentially affected stakeholders, early in the planning of the project and continue these activities throughout the lifecycle of the project.
The CER also conducts engagement activities, such as public information sessions and training support for participants involved in the application review and hearing process. The CER is committed to using transparent processes that are built on engagement and inclusive participation. The CER also considers the best available scientific information, data, and Indigenous knowledge in decision-making.
Potential issues identified by landowners, municipalities and other stakeholders during these activities were captured in the Summary Issues Letter and Report and shared with the Commission of the CER and the company.
The Crown Consultation Coordinator conducted engagement activities with Indigenous Peoples. This included information sessions that focused on the CER’s role and the hearing process along with identifying potential issues, interests and suggestions.
These were then captured in the Early Engagement Report and shared with the Indigenous Peoples involved, the Commission and the company.
Disclaimer: Please note that documents in the CER’s Regulatory Documents repository (REGDOCS) are translated in accordance with the Official Languages Act, which does not result in the translation of every document into both official languages.
Participating in a hearing
The level of participation in the hearing process should be based on how much the project will impact your interests.
Intervenors
Intervenors must explain how an application impacts their interests and why intervenor status is required. Being an intervenor requires a time commitment and may involve costs to prepare and submit evidence. This includes submitting written evidence, asking questions about evidence, submitting and responding to motions, and making a final argument. If you would like to become a late intervenor, submit your application in the Participation Portal.
Commenters
Commenters may share their views with the Commission in a Letter of Comment that will be placed on the public record. However, commenters can’t ask questions about the evidence or present it in person at a hearing. To submit a Letter of Comment, follow the instructions outlined in the Participation Portal.
The latest details regarding the hearing can be found on the Hearings, Workshops, Information Sessions, and Conference page.
Process help
Process Advisors are available to answer questions, host training and information sessions, and provide process information and assistance on how to effectively participate in the hearing. The Participant Toolbox offers helpful resources such as templates and step-by-step instructions for intervenors. Learn more about the role of a Process Advisor.
How can we support you
Contacts
Get Information
Process Advisor Team
Canada Energy Regulator
E-mail: PouceCoupeT2Gproject@cer-rec.gc.ca
Telephone (toll free): 1-800-899-1265
Facsimile: 403-292-5503
Facsimile (toll free): 1-877-288-8803
Media Relations Team
Canada Energy Regulator
Email: media@cer-rec.gc.ca
Telephone (toll free): 1-800-899-1265
Crown Consultation Team
Canada Energy Regulator
Email: crownconsultationpoucecoupe@cer-rec.gc.ca
Telephone (toll free): 1-800-899-1265
- Date modified: